What are the types of work breakdown structure?

A Work Breakdown Structure (WBS) is a hierarchical outline of the tasks required to complete a project. The WBS “breaks down” the structure of a project into manageable deliverables.

A Work Breakdown Structure (WBS) is a hierarchical outline of the tasks required to complete a project. The WBS “breaks down” the structure of a project into manageable deliverables. Each deliverable is assigned a task, or series of tasks that can be further broken down into subtasks to meet the needs of the project.

The advantage of using a WBS as part of project lifecycle management is that is takes large, complex projects and breaks them into smaller, more manageable tasks that can be assigned to specific people or teams to deliver.

Purpose of the Work Breakdown Structure

The primary purpose of the WBS is too plan the schedule for the project. Each task duration is planned in conjunction with its required predecessors and following tasks. The WBS then provides an overall plan so that the project manager can see how the project should progress and manage the workflow appropriately.

Related: What is a Cost Breakdown Structure?

WBS Components

The parts of the WBS include:

  • Tasks – a number, ID, title, and description of each task.
  • Task Owner – who is responsible for completing the task.
  • Task Dependency and Predecessors – linking two tasks together if one depends on the completion of the other.
  • Start and Finish Date of Task – estimates the time each task will take and ultimately the entire project.
  • Duration – how long will each task take on the calendar (usually number of days or hours).
  • Work Estimate – how many hours/days of work are required to complete the task (combining all resource hours together if working in parallel).
  • Task Status – whether each task is assigned to an owner/resource, started, in progress, late, complete, etc.
  • Gantt Chart – a visualization of the WBS with tasks represented graphically over time.

Work Breakdown Structure Example

The WBS is a central component of Project Business Automation, as it acts as the primary schedule against which all other activities and system operations are executed.

See How the Work Breakdown Structure in PBA Works

What are the types of work breakdown structure?

Watch this video on YouTube

Eliminate standalone project management applications and the overhead needed to manage them.

  • Leverage the project schedule to accurately build a labor budget, time-phase earned value estimates, and generate cash flow projections
  • Apply the timeline directly to MRP for production orders, and automatically constrain the schedule based on procurement or production delays
  • Staff projects more efficiently and automatically feed status updates, issues and work estimates back to the schedule from the timesheet
  • Evaluate cost to complete with real-time work estimates from the schedule
  • Report on the financial impact of schedule changes immediately

To learn how a WBS should be integrated into the rest of your project processes and systems, Download the Project Business Automation Blueprint. It is the definitive guide to creating a comprehensive business system for your Project Business that ties together your project operations and financials seamlessly.

What are the types of work breakdown structure?

The Difference Between WBS and CBS

The WBS is an operational plan – what work will be done, how it will be completed and on what schedule. The Cost Breakdown Structure (CBS) is the financial plan of the project. Many companies use the WBS as their financial plan as well. However, this approach often leads to financial problems with the project. The WBS is far to granular to be able to manage costs effectively. Or, it can be far to general to get the right cost details and apply them to the appropriate general ledger areas.

The CBS is the answer. The CBS is linked to the WBS, but allows for a complete breakdown of the project for financial purposes, which enables effective project cost control and earned value analysis.

A Work Breakdown Structure (WBS) is a tool used to define a project in discrete work elements in a Hierarchical format. It displays and defines the product, or products, to be developed and/or produced. It relates the elements of work to be accomplished to each other and to the end product. In other words, the WBS is an organized method to break down a product into subproducts at lower levels of detail. It’s used for planning, cost estimating, execution and control.

Advertisements

Definition: A Work Breakdown Structure is a hierarchical decomposition of work tasks that need to be performed by project team members to accomplish project goals and objectives and create the required deliverable.

Purpose of the Work Breakdown Structure (WBS)

The purpose of the WBS is to break down projects into manageable pieces, allowing for better planning, cost estimating, execution and control.

Example of a Work Breakdown Structure (WBS)

WBSWBS Example from SMC Systems Engineering Handbook

Why Develop a Work Breakdown Structure (WBS)

The WBS is a means of organizing system development activities based on system and product decompositions. It is a product-oriented family tree composed of hardware, software, services, data, and facilities, which result from systems engineering efforts during the development and production of the system and its components, and which completely defines the program. The WBS is prepared from both the physical and system architectures and identifies all necessary products and services needed for the system. This top-down structure provides a continuity of flow down for all tasks. Enough levels must be provided to properly define work packages for cost and schedule control purposes. [1]

Advertisements

The Benefits of a Work Breakdown Structure (WBS) are:

  • Organizes the project deliverables and tasks
  • Determines the program schedule (Integrated Master Schedule)
  • Enhances communication
  • Details tasks and dependencies
  • Identifies all products and services a system needs
  • Helps determine cost estimates
  • Identify Project Phases

The Two Types of Work Breakdown Structures (WBS)

The Program Manager (PM) is usually responsible for developing an overall program WBS and initiating the development of contract WBSs for each contract in accordance with common DoD practice established in Mil-HDBK 881. The two types of WBS on a program are:

  • Program WBS: A program WBS is established to provide the framework for program and technical planning, cost estimating, resource allocation, performance measurement, and status reporting. The WBS defines the total hardware, software, services, data, and facilities system and relates these elements to each other and to the end product. Program offices develop a program WBS tailoring the guidance provided in MIL-HDBK-881 and MIL-STD-881D. The WBS is also an integral part of the preparation of the Cost Analysis Requirements Description (CARD).
  • Contract WBS: are part of the program WBS and relate to deliverables and tasks on a specific contract.

Initial Work Breakdown Structure (WBS) Development

With the support of systems engineering, the PM develops the first three levels of the program WBS and provides contractors with guidance for lower-level WBS development. As with most standards and handbooks, the use of MIL-HDBK-881 cannot be specified as a contract requirement. Though WBS development is a systems engineering activity, it impacts costing, scheduling, budgeting professionals, and contracting officers. An integrated team representing these Stakeholders is needed to support WBS development. [1]

Advertisements

Work Breakdown Structure (WBS) Guidance (MIL-STD-881)

A WBS provides a consistent and visible framework for defense materiel items and contracts within a program. Mil-Standard 881D offers uniformity in definition and approach consistency for developing all WBS levels. Generating and applying uniform work breakdown structures improves communication in the acquisition process. It also provides direction to industry in extending contract work breakdown structures. [1]

Standard: MIL-STD-881D “DoD Standard Practice WBS for Defense Materiel Items”

Work Breakdown Structure (WBS) Levels

The first three Work Breakdown Structure (WBS) Levels are organized as follows:

Advertisements

  • Level 1: Overall System
  • Level 2: Major Elements (Segment)(Main Project Phases)
  • Level 3: Subordinate Components (Prime Items)(Groups of Tasks)

 

Advertisements

Example: WBS Levels

How to Make a Work Breakdown Structure (WBS)

The process of developing a WBS is straightforward but requires preparation and a clear understanding of what is required to be accomplished on a project.

Advertisements

  • Step 1: Gather Main Documentation: You must understand the project goals and objectives. To do this, gather the project charter,  scope, objectives, and any requirements.
  • Step 2: Identify Your Main Team Members: A WBS can’t be built in a vacuum. It takes a team of specialized people to know how to break their sections down into discreet parts.
  • Step 3: Define WBS Level 1: This level is a summary of the deliverable that must be met to satisfy the project scope.
  • Step 4: Create the WBS Levels: This is the step where you break down is WBS component into discreet events. This is the most time-consuming and important step in the process. You need to break down the work until each Element can be accomplished by a single individual or organization.
  • Step 5: Create the WBS Dictionary: The Dictionary describes each work element in the WBS.
  • Step 6: Create the Integrated Master Schedule (IMS) and Integrated Master Plan (IMP): This creates a complete plan of all the work that needs to be accomplished and by when.

How to Utilize a Work Breakdown Structure (WBS)

A Work Breakdown Structure is primarily used as a planning tool to help the Program Manager and project personnel plan, define and organize a project into discreet deliverables. It describes all the work that needs to be accomplished to help avoid any confusion. There are three main components of a WBS that help with defining the program. These are:

  • Control Accounts: Control Account (CA) is a management control point at which budgets (resource plans) and actual costs are accumulated and compared to earned value for management control purposes. Any WBS Elements at which the project plans to monitor and report performance.
  • Planning Packages: These are steps that have been created but are not fully defined yet into work packages.
  • Work Packages: A work package is simply a task/activity or grouping of work and is the point at which work is planned, progress is measured, and earned value is computed. Natural subdivision of a Control Account. This information is described in the WBS Dictionary.

Example: WBS Deliverable Levels

Control Accounts in the Work Breakdown Structure (WBS)

Control Accounts are WBS Elements at which the project plans to monitor and report performance. The Control Accounts can be any Element in the WBS. To assist with the monitoring and reporting, project management information tools are used to collect, analyze and report information at any Element within the WBS.

Work Packages in the Work Breakdown Structure (WBS)

Work Package (WP) is simply a task/activity or grouping of work and is the point at which work is planned, progress is measured, and earned value is computed. It can be translated into different terms in different companies and functions. It can be a design job, a tool design package, a build-to-package, a shop order, a part number, a purchase order, or any other definable task/activity at whatever level of control is normal for program management within the company. They normally represent the lowest level of a WBS.

Work Packages Example

Work packages come in a variety of formats, but the most common format is in the WBS. Below is a WBS, and the work packages are at the bottom level.

Example of Work Packages in a Work Breakdown Structure (WBS) Format

Work Breakdown Structure (WBS) Application Tools

There are a variety of application tools you can use in the development of a WBS. Below are some of the example types that can be used.

  • Nodal Chart: A graphical representation of the deliverables in nodes.
  • Flowchart: The most common WBS application
  • Gantt Chart: You can show task dependencies and show project milestones.
  • Spreadsheet: A WBS can be created in a spreadsheet detailing the different levels and phases in columns and rows.
  • List: A simple list of deliverables. Best used for a simple WBS.

Contractor Work Breakdown Structure (WBS)

The contract WBS is the Government – approved WBS for program reporting purposes and includes all program elements (for example, hardware, software, services, data, or facilities), which are the contractor’s responsibility. It includes the contractor’s discretionary extension to lower levels, in accordance with Government direction and the contract Statement of Work (SOW).

Work Breakdown Structure (WBS) Dictionary

The WBS Dictionary is a document that describes each element work package in a project component of the WBS. These elements can include milestones, deliverables, activities, scope, resources, costs, and quality. The main purpose of the WBS dictionary is to define and communicate the work in more detail to help those working on an element or work package understand what needs to be done.

What are the 3 levels of Work Breakdown Structure?

Work breakdown structure levels.
Level 0: Project title or final deliverable..
Level 1: Major deliverables..
Level 2: Deliverables that can still be broken down..
Level 3: Can be assigned to the team to complete the third level deliverables..

What are the 4 levels of Work Breakdown Structure?

At the top level is the project ultimate goal, the second level contains the project outcomes, the third level has the project outputs, and the fourth level with activities. Depending on the size and complexity of the project, the WBS may contain a fourth level that describe the tasks.

What are the two types of WBS used in DOD?

The types of WBS are categorized as who control and maintain the WBS. Program WBS is controlled and maintain by the program management office. Contractor WBS is controlled and maintain by the contractor. The number of contractor WBS' are depended on the number of contracts of a program.

What is Work Breakdown Structure with example?

“A work breakdown structure defines all the things a project needs to accomplish, organized into multiple levels, and displayed graphically.” Essentially, the WBS defines the “what” of the project. Everything you need to accomplish in the project is displayed in a single, easy-to-understand chart.