How long can activity C be delayed without delaying the completion of the project

Leads, lags and float are concepts used in schedule development process. The process of schedule development includes: identification of all activities, sequencing all activities based on dependency, estimating duration of each activity and finalizing the schedule. Leads, lags and float are used as part of activity sequencing process. All activities once sequenced will form a schedule network diagram. Let us first look at the definition of all these three attributes.

Float

Float (also known as slack) is the amount of time by which the start of an activity can be delayed without delaying the project completion time. Every task will have following set of start and finish time. 

  • Earliest start time (ES) - The earliest time, an activity can start once the previous dependent activities are over.
  • Earliest finish time (EF) - This would be ES + activity duration.
  • Latest finish time (LF) - The latest time an activity can finish without delaying the project.
  • Latest start time (LS) - This would be LF - activity duration.

Float time of an activity can be calculated by taking the difference between Late Start (LS) and Early Start (ES) OR between Late Finish (LF) and Early Finish (EF).

Float = LS-ES  OR 

=LF-EF

A positive float time indicates the flexibility we will have in delaying the specific activity without delaying the project completion time.

Typically, while doing scheduling, the critical path tasks will have zero float and the non-critical path tasks will have a positive float. That means non-critical path tasks can be delayed to certain extent without compromising on the project completion time. Float time information of tasks is very useful to the project team for taking scheduling decisions when there will be resource constraints.

Lag:

Lag is the amount of wait time between two tasks. Or in other words, lag is the amount of time by which a successor activity will be delayed. Lag can be used in all the four logical relationships in scheduling, such as Finish-to-start (FS), start-to-start (SS), finish-to-finish (FS) and start-to-finish (SF).

In below example, Task A and B have a Finish to Start (FS) relationship. Ideally both A and B should get finished on the 12th day. But when we insert a waiting of time of 2 days before B can start, then both A and B will get completed only on the 14th day.

How long can activity C be delayed without delaying the completion of the project

Lead:

Lead is the amount of time a successor task can be accelerated. Lead can applied only on finish-to-start relationship between two activities. We can see the below example. In the below example, task B can start 2 days before the completion of task A. Hence the start of task B, which ideally would have been on 6th day, will not start on 4th day.

Conclusion:

Float, lead and lag are very important concepts and information for the scheduling team. A PMP training course ensures you get a hold of these concepts. These are used to optimally identify the dependencies and the associated constraints. Float information is useful in resource allocation when there are resource constraints. Lead is used for accelerating start of tasks (fast tracking) for reducing project timelines. Lag is used for ensuring that required idle or wait time after a task is appropriately provisioned.

Students also viewed

Chapter 6

41 terms

OSM Chapter 5

25 terms

CH15

40 terms

MGMT 435 CHAPTER 10 *

19 terms

Sets found in the same folder

Chapter 14

40 terms

MGT3121 Ch 16 MC

20 terms

MGMT 435 CHAPTER 11 (Done)

47 terms

MIS 380 Test 1 MCQ

42 terms

Other sets by this creator

Chapter 15

40 terms

Chapter 9 Market Efficiency and Behavioral Finance

42 terms

Chapter 6 Common Stocks

68 terms

Chapter 8 Stock Valuation

68 terms

Recommended textbook solutions

How long can activity C be delayed without delaying the completion of the project

Information Technology Project Management: Providing Measurable Organizational Value

5th EditionJack T. Marchewka

346 solutions

How long can activity C be delayed without delaying the completion of the project

Human Resource Management

15th EditionJohn David Jackson, Patricia Meglich, Robert Mathis, Sean Valentine

249 solutions

How long can activity C be delayed without delaying the completion of the project

Operations Management: Sustainability and Supply Chain Management

12th EditionBarry Render, Chuck Munson, Jay Heizer

1,698 solutions

How long can activity C be delayed without delaying the completion of the project

Human Resource Management

15th EditionJohn David Jackson, Patricia Meglich, Robert Mathis, Sean Valentine

249 solutions

Other Quizlet sets

MGMT Ch 11

40 terms

Can critical activities be delayed?

Any delay in an activity on the critical path would reduce the amount of total float available on the project. A project can also have negative float, which means the calculated completion date of the last activity is later than the targeted completion date established at the beginning of the project.

Is the maximum amount of time an activity can be delayed without extending the overall project completion time?

Total float: The time span by which starting or finishing of an activity can be delayed without delaying the completion of the project. It is the maximum available time over the activity completion time.

Is the amount of time an individual activity in a network can be delayed without delaying the entire project?

Slack is the amount of time an activity can be delayed without delaying the entire project.

What is the duration by which an activity can be delayed without delaying?

The Interfering float is the time available to delay an activity without delaying the project\'s estimated completion time, but delaying an activity into interfering float will delay the start of one or more following non-critical activities.